Guidelines for Obtaining Electric Service

For new construction or new manufactured housing location

Following these steps will help you through the requirements for locating/constructing a new electric service.

  1. Obtain your address from the county 911 information center.
  2. Contact Holston Electric Cooperative’s (HEC) engineering department and request a staking layout. Your staking request should be completed in the name of the person who will be paying the electric bill. You should refer to this same account name whenever inquiring about this job.
  3. After the staking layout is finished, the staking engineer can tell you what the costs for your electric service will be:
    • Connection Fee __________
    • Meter Set Fee __________
    • Aid to Construction __________
    • Other __________
    The engineer will compose a work order in the same name as the staking application.
  4. You will need to purchase a sewer permit from the health department or the local city department where sewer service is available. The sewer permit and your 911 address are required by the state wiring inspector.
  5. When steps 1, 2 and 3 are completed and your site is ready for electric service connection, visit the HEC office in Rogersville, Church Hill or Russellville to complete an application for service and pay the required deposits and fees. You may also print out the application for membership and service and return the completed application by fax or mail. The state wiring permits can also be purchased from any HEC office at this time.
  6. Make an appointment with the state wiring inspector. To schedule your inspection, you may call or come by the cooperative office and speak to the state inspector during the following times: Tuesdays and Thursdays, 8:00 – 9:00 a.m. at the HEC office in Rogersville, (423) 272-8821.
  7. The state inspector will notify HEC when the wiring is approved and ready for connection.
  8. After the inspection, you may call the HEC construction department to get a tentative date for service connection. Please refer to the original account name when obtaining information.
  9. Service connections are scheduled on a first-come, first-served basis, and are built as soon as a crew becomes available (usually within 4 or 5 days.) If the new service is a single- or double-wide manufactured home, you are now ready for electric service. Steps 9 and 10 do not apply for your service request.
  10. If the new service is a site built home and you now have a temporary service, contact HEC engineering department to determine the meter location before wiring the house. The engineer will prepare a work order for the permanent service.
  11. After the meter location is marked, permanent wiring can begin in the house. You must purchase a rough-in permit, a final permit, heating permit and schedule inspections with the state wiring inspector as you become ready.
  12. The state inspector will notify the HEC construction department when all inspections are complete. At this time the permanent service work order will be scheduled with the construction department.

To help us serve you better, please remember to refer to the same account name throughout this process.